Edwards EST3 to EST4 Migration
Why migrate.
EST3 is mature; Edwards’ current platform is EST4 with extended capacity, networking, and notification appliance support. Buildings on EST3 face: manufacturer end-of-support horizons, parts availability tightening on legacy interfaces, and ITM efficiency gains from EST4’s diagnostic improvements. Migration earns the capital when the platform is approaching support-end and the building is going to need a transition within five years anyway.
What survives the migration.
Most addressable device schedules. The riser wiring infrastructure (subject to §12 survivability check). Most notification appliance circuits. Programming logic — Edwards provides migration tooling. The acceptance-testing process under §10 has to happen at full scope; the platform is new from the AHJ’s perspective.
What gets replaced.
The panel. The amplifier(s) on voice evac configurations. The addressable loop interfaces (LSC/SLC). Network communication modules. Operator interface (the legacy EST3 LCD goes; EST4’s higher-resolution display arrives).
Tyrian's migration pattern.
- Audit-grade walk: existing EST3 platform documentation, device schedule export, programming archive.
- NICET IV migration design with AHJ first-pass-approval target.
- Phased install scheduled in construction windows to avoid occupant impairment.
- Acceptance testing with AHJ inspector on-site for sign-off.
- Clause 12 handover at completion: building owner receives EST4 programming files and credentials.
EST3-to-EST4 FAQs.
Will my addressable devices need to be replaced?
Most are reusable on EST4 SLC loops. Some legacy device families have replacement requirements; the migration design specifies.
Can it be done without occupant impairment?
Yes – Tyrian’s pattern is phased install scheduled in construction windows.
What about my voice evac amplifiers?
Amplifiers get replaced. The notification appliance circuits and audio paths are preserved where possible.
How much does EST3-to-EST4 cost vs. full replacement?
Building-dependent — typically 35-50% less than full rip-and-replace because the wiring infrastructure is preserved.